Building A:
• ° Kitchen installation almost ready
• ° A/C installations ongoing
•
• ° Rectification works ongoing
• ° Lift to be tested and certified
• ° Filling swimming pool
• ° Rear road work to start
Building B:
• ° Topping 3rd floor ready
• ° Columns from 3rd floor started (70% done)
• ° Formwork for beams 4th floor started
• ° Stair formworks from ground floor started